Mason City Mayor Bill Schickel adjourns the city council's special meeting to terminate the city's development agreement with G8 Development at City Hall in October.

MASON CITY | At his state of the city address on Wednesday, Jan. 2, Mayor Bill Schickel made it known that a major goal for 2019 was to finally build the long-promised multipurpose arena as part of the River City Renaissance Project. 

Thursday afternoon that plan moved incrementally forward with the announcement of five contractor bids for demolition and excavation to ICON Architectural Group who is designing and coordinating the building of the arena.

On the low-end was Charlson Excavating Co. Inc, which bid $291,500, while Larry Elwood was on the high side and came in at $849,662.

That bid table was provided by City Administrator Aaron Burnett whose target approval for the bids is within a week. "We intend on taking action at the council meeting next Tuesday," Burnett said.

Multipurpose arena bids

For demolition and excavation

Contractor Bid
Carl A. Nelson & Co. $599,990
Charlson Excavating Co. Inc. $291,500
Dean Snyder Construction $423,500
Henkel Construction $538,000
Larry Elwood Construction $849,662

The next "bid package," which focuses on "structural steel, concrete foundation and ice plant," is slated for a 14-day bid window and a request for city council approval on Jan. 29. 

"Bid Package 3" will follow in March and deal with mechanical, electrical and interior "fit-up." It's scheduled for a two-week bidding period and then a request for city council approval on April 2. 